Key Points to be Remembered
· There are many factors affect the time span of planning, among the most important of them:
(a) The expected degree of change.
(b) The size and degree of complexity.
(c) The nature of the product of service.
(d) The needed and the available resources.
· There is a relationship between the job level and the timing of planning.
· There are many methods and techniques for short-term planning, among the most important of them:
(a) Gantt chart.
(b) PERT system.
· Gantt chart is essentially a bar graph with time on the horizontal axis and the resources to be scheduled on the vertical axis.
· PERT = Program Evaluation and Review Technique: is a network of project activities showing both the estimates of time necessary to complete each activity and the sequence of activities that must be followed to complete the project.
· There are many steps to be followed for developing the PERT network.